![]() The scoping study hasd confirmed route three as the preferred route of the Navan line.
Route 1 is the old alignment to Navan Junction where the new Navan Central will be built. Route 2 is the old alignment with an extension to the Kells road for an additional Park and Ride to ber called Navan North. Route 3 is the old route with a deviation to the M3 interchange at Dunshaughlin, returning to the old alignment but deviating west around Kilmessan. From the the old alignment is used until Cannistown /M3 where the line deviates behind the new houses and rejoins the alignment to join the Drogheda line for Navan Central, terminating there. The Trim road station no longer figures. Route 4 went into Dunshaughlin but would have cost €55m more because of having to go below 2 new roads and over the M3 twice. All other five routes were discounted for the usual reason and as Ratoath cannot grow anymore as it has no more capacity for services (sewerage etc) and Ashbourne is too far. Pros: Route has finally been selected. Cons: Iarnród Éireann have said it is not a financially viable project as even though it will cover it's running costs as project and will be economically viable as revenue will not cover depreciation. And €78 million has been landed on the project for the second hand rolling stock that would be used. Estimated cost €450m at todays prices, €580 at 2015 figures. IÉ claim section 49 levies will not cover costs (not with the 1km radius on the Dunboyne model anyway). IÉ claim 1hr journey time to Docklands at best saying it will be uncompetitive with roads. IÉ claim that they have no access to Tranport 21 costings but that they have been told that the funding is not in Transport 21 for that amount as it exceeds the Transport 21 costing by €200m - work out the maths. The are recommending abandonment of the project as it does not offer the same value as other competing projects in Transport 21. Footnote - Sewer pipe gets moved if built. Last edited by Navan Junction : 08-01-2008 at 23:07. |
![]() |
![]() |
#2 |
Registered user
Join Date: Dec 2005
Location: Kildare
Posts: 1,555
|
![]() Its my news to the masses.
![]() Im putting it in here because it has a wider (and deservedly so) interest than just RUI members. Yes its an infrastructural issue, but its dynamite. The news may have broken elsewhere, but here goes. IE made a presentation to Meath CC today in relation to the routes and costings for the rail line from Pace to Navan. The same presentation is being made to the DOT next week. Tom Finn of IE is running the show. Some of the route options examined were bonkers, but the preferred route (option 3) is more or less the original alignment with the necessary deviations. Navan station is to be sited at the site of Navan junction. (The original site on the former railway.) Sounds good so far, doesn't it? But Tom Finn stated that the costings in T21 for the project were not from IE and perhaps they came from the strategic rail review of 2003. Either way he wasn't sure where the figure was plucked from, but he was adamant that it was short by 200 million! Do the maths folks. There's more! The project would not recoup its build costs. It would cover its running costs, but not the cost of depreciation. Therefore the document reaches the conclusion that the project is not financially viable. Of course this doesn't mean that the line won't be built, but I feel its is a very convenient method of placing it on the back burner. Yet again my "banjo bet" looks safe and a further prediction from Dero's crystal ball.......if the dept of finance don't fancy the monopoly money that the direct route will cost, then the Drogheda route looks like a sleeping possibility. This particular report is almost identical to a previous report done by IE and MCC. (circa 19999) That too concluded running as far as Navan wasn't viable. In fact its recommendation was to run as far as Pace and build a huge P+R for Navan commuters. The more eagle eyed amongst you will remember a debate between Barry Kenny and I on the last word in mid 2005, where he tried to justify the Pace P+R as a suitable facility for Navan commuters. Thats what it was always meant to be. Of course in November 2005 T21 pulled a rabbit out of the hat by including Navan in the list. Apparently the money was "ringfenced". But according to Tom Finn today that "ringfenced" money is a tad short. (If its even there at all) I don't like saying these things and I know I sound like the Eamonn Dunphy of transport, but I still don't believe that Navan or the Interconnector will be built. Alternatively, it could be Navan or the Interconnector. Take your pick. Meanwhile in the west, the WRC is on its merry way. And yes, it was mentioned by one councillor in Meath, who made the very funny point that "the WRC will carry 500 people a day and thats the population of Kilmessan!" Thats all from the funny farm. |
![]() |
![]() |
#3 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() So its exactly in line with the submission we made all that time ago, we wanted the Dunshaughlin deviation and we got it
And its nothing new that the project was going to be too expensive
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
#4 |
Registered user
Join Date: Dec 2005
Location: Kildare
Posts: 1,555
|
![]() Ive posted more or less the same in a different thread which crossed with this one.
The only real points of interest in todays news in relation to P11/RUI are of course the sewer pipe and the fact that I went on record saying that the won't happen by 2015. The submission is merely routine and from my perspective unimportant as I never believed it would happen anyway. I say that with respect to my former colleagues here. The correspondence I have in relation to the project will make interesting reading and Im baking the humble pie for the few that will have to eat it. As I said in the other thread, Drogheda is now the only realistic hope for Navan. What a mess. |
![]() |
![]() |
#5 | |
Membership Officer
Join Date: Dec 2005
Location: Maynooth
Posts: 1,116
|
![]() Quote:
I'm firmly in the Interconnector not being built camp (well maybe by 2025) also ![]() |
|
![]() |
![]() |
#6 | |
Registered user
Join Date: Dec 2005
Location: Kildare
Posts: 1,555
|
![]() Quote:
As for the interconnector. Brilliant idea. IE are up for it. It needs to happen. Don't rule out IE scheming against Navan to protect it. But isn't it sad that we have to think like this. |
|
![]() |
![]() |
#7 |
Membership Officer
Join Date: Dec 2005
Location: Maynooth
Posts: 1,116
|
![]() I just think the scandalous waste of our (brief) wealth from the boom times will come back to haunt us.
There has been little in the way of a capital legacy laid down for the people who helped fund the whole boom, the first time buyers out in places like Navan etc. They have enslaved themselves to long mortgages, long commutes all to work hard to give up taxes for nothing in return. Truely sad state of affairs. As an aside, before the election I was hassling my local candiate (Michael Fitzpatrick FF TD now) about how much room for improvement there was in the Maynooth line service and he turned to me and said in the most patronising manner about how lucky I was to have the service. How right the arrogant sh1te was. |
![]() |
![]() |
#8 | |
Registered user
Join Date: Dec 2005
Location: Kildare
Posts: 1,555
|
![]() Quote:
|
|
![]() |
![]() |
#9 |
Member
Join Date: Dec 2005
Posts: 378
|
![]() Y'all will have a motorway ... Yee Ha . Don't forget it'll be tolled!
|
![]() |
![]() |
#10 | |
Registered user
Join Date: Dec 2005
Location: Kildare
Posts: 1,555
|
![]() Quote:
Anyway, Im divulging widely. This is about Navan and the implications. |
|
![]() |
![]() |
#11 | |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() Quote:
Remember we said to would could 300 million (at 2004 prices), well we are proven right 455 less the rolling stock cost (which is normally separate) gives about 300 million
__________________
Unhappy with new timetable - let us know |
|
![]() |
![]() |
#12 |
Member
Join Date: Feb 2006
Location: Paris
Posts: 78
|
![]() So, as I understand it:
- Pace to Navan will never happen - Drogheda to Navan could be a runner - Financing a rail project to Navan could jeopardise finance for the Interconnector. Those who always predicted this situation are justified in making it known that they were right all along. P11/RUI members do need to give themselves a pat on the back every now and then, and we need this for "attacking" IE and the government. However, I suppose RUI needs to quickly move on and deal with the scenario. I'm just a fly-on-the-wall member so I was wondering how the really active members think RUI policy will evolve on this issue? |
![]() |
![]() |
#13 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() We predicted this more or less, Navan would be the first casualty.
The first person to let it slip was Dick Fearn CEO of IE who in a published interview clearly stated it wasn't a certainty that was back in spring 2006 In terms of the route, we where proven 100% on every single aspect. We didn't say East or West of Killmessan (west was the obvious choice) but everything else we got spot on. We did make a submission (so its on record for all to see) and we did speak at considerable length with the IE people working on the route choice right down to the manholes (proven right there as well) On cost yet again we hit very close We are not really in the infrastructure business for this very reason we know what should be done but there is very little support to achieve this However it must be emphasised that the Navan line will cover its operational costs the WRC will not and the costs at todays prices are not much different No annual passenger number quoted in the reports but we think its in the 2-2.5 million bracket Its all speculation really until we see a copy of this report, it would be most inappropriate to issue a formal statement until that time
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
#14 |
Really Regular Poster
Join Date: Feb 2006
Location: Navan
Posts: 305
|
![]() Not speculation. I've read the report twice
|
![]() |
![]() |
#15 | |
Registered user
Join Date: Dec 2005
Location: Kildare
Posts: 1,555
|
![]() Quote:
![]() While no longer a committee member, I'd suggest that the Drogheda angle be taken off the shelf and put into the media again. IE themselves have now removed one of the reasons they used against this proposal. If the interconnector was built, then loads of trains could run from Navan on the northern line. Drogheda would be the logical reaction from this organisation. |
|
![]() |
![]() |
#16 |
Member
Join Date: Apr 2007
Posts: 94
|
![]() As a matter of interest, how many T21 rail projects are financially, as opposed to economically, viable? Pace isn't (http://www.meathontrack.com/uploads/...rt.pdf#page=26) and neither is Midleton (I can no longer locate the study online, but it's discussed on pages vii and viii, or 7 and 8 of the pdf - and probably at greater length elsewhere - for anybody with a saved or paper copy; the study states that "there are few rail projects which can be justified solely on financial grounds"). I think I remember reading somewhere that the only project emerging from the Dublin Suburban Rail Strategic Review as financially viable was the Phoenix Park Tunnel.
It might be that the economic results were unsatisfactory, but nobody's actually said so. Of course, the points about costings and population growth are valid ones. |
![]() |
![]() |
#17 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() We need to see the report to see exactly what it says, what assumptions and so on
Midleton is in fact profitable
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
#18 | |
Member
Join Date: May 2006
Location: Dublin
Posts: 608
|
![]() The Irish Times article above says:
Quote:
__________________
! |
|
![]() |
![]() |
#19 |
Really Regular Poster
Join Date: Feb 2006
Location: Navan
Posts: 305
|
![]() Yup, once born it will breath on it's own
Financially speaking that is |
![]() |
![]() |
#20 | |
Registered user
Join Date: Dec 2005
Location: Kildare
Posts: 1,555
|
![]() Quote:
Its also worth noting that IE havent just said its unviable on financial grounds. They have recommended that the project be abandoned. The longer people tolerate this charade and fool themselves into believing that the direct route will happen, the less likely Navan will get a rail service. Last edited by Derek Wheeler : 08-01-2008 at 18:37. |
|
![]() |
![]() |