Thread Tools | Search this Thread | Display Modes |
|
![]() |
#1 |
Regular Poster
Join Date: Dec 2007
Location: Cambridge
Posts: 131
|
![]() Good thing they've turned the power on then
![]() |
![]() |
![]() |
![]() |
#2 |
Local Liaison Officer
Join Date: Dec 2006
Posts: 5,442
|
![]() Progress as of 1 March 2011. All photos have captions.
__________________
Last edited by Colm Moore : 12-03-2011 at 16:51. |
![]() |
![]() |
![]() |
#3 |
Local Liaison Officer
Join Date: Dec 2006
Posts: 5,442
|
![]() More
__________________
Last edited by Colm Moore : 12-03-2011 at 16:48. |
![]() |
![]() |
![]() |
#4 |
Local Liaison Officer
Join Date: Dec 2006
Posts: 5,442
|
![]()
__________________
|
![]() |
![]() |
![]() |
#5 |
Member
Join Date: Dec 2005
Posts: 541
|
![]() Can anyone familiar with the area tell me how well developed it is? Is it likely to suffer the same fate as the south end of the Brides Glen extension? I know the hotel and conference center were seen as trip generators but I'd imagine both of those are at risk in the short term.
|
![]() |
![]() |
![]() |
#6 |
Really Really Regluar Poster
Join Date: Aug 2006
Location: Toronto, Canada
Posts: 1,371
|
![]() Is there any ballasted track on the LUAS network? Seems to be a lot of slab in those pictures and some I've seen of Green Line.
|
![]() |
![]() |
![]() |
#7 | |
Local Liaison Officer
Join Date: Dec 2006
Posts: 5,442
|
![]() Quote:
Cherrywood: http://www.bing.com/maps/?v=2&cp=sw7...&FORM=LMLTC C The NTA's 2030 vision suggests extending it to Greenogue http://www.bing.com/maps/?v=2&cp=swg...&FORM=LMLTC C The real problem is getting from the housing estates to the stops - in some cases there are huge detours. I have complained about access and I'm not sure what has been done, if anything. http://maps.google.ie/maps?f=d&sourc...08991&t=h&z=16 There is a mix of slab, ballasted and there is another type (where the track is flush with the surface and used at stops and roads), but the name escapes me.
__________________
Last edited by Colm Moore : 13-03-2011 at 07:11. |
|
![]() |
![]() |
![]() |
#8 | |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() Quote:
Ballasted track is cheaper to install but more expensive to maintain but offers more flexibility
__________________
Unhappy with new timetable - let us know |
|
![]() |
![]() |
![]() |
Thread Tools | Search this Thread |
Display Modes | |
|
|