![]() Word has come through that strike notice has been served by a group of permanent way staff based in Cork.
This arrises due to employment of contractors to work on the Midleton project. As of yet we have no details on the date upon which the strike is likely to begin
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
![]() |
#2 |
Really Regular Poster
Join Date: Jan 2006
Posts: 767
|
![]() This is the same group which went on a wildcat/lightning strike a year or so ago. What is it with Cork, something in the water supply?
|
![]() |
![]() |
![]() |
#3 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() Same group. They seem to take the view that they have first refusal on all trackworks anywhere in the region
Midleton is deemed a brand new line, so a lot of it has been subcontracted
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
![]() |
#4 |
Member
Join Date: Dec 2005
Location: Northern line
Posts: 1,311
|
![]() Ah the rebel county.. Micheal Collins, Roy Keane, Georgie O'Callaghan, train drivers and now the track repair staff..
[Insert names of wingy rebels where appropriate] |
![]() |
![]() |
![]() |
#5 |
Membership Officer
Join Date: Dec 2005
Location: Maynooth
Posts: 1,116
|
![]() |
![]() |
![]() |
![]() |
#6 |
Regular Poster
Join Date: Oct 2007
Location: Dublin
Posts: 106
|
![]() Oi, leave us Rebels alone!!!
![]() |
![]() |
![]() |
![]() |
#7 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() This appears to be a chance your arm operation. Demand first refusal on work but then won't agree to actually do it unless they feel like it.
Same thing with contractors is ongoing in the other two permanent way divisions but they aren't up in arms. Quite different to the drivers issue, who seem to have been targeted and victimised. Irish Rail might remove its head from the sand at about 16:45 and place a sneaky notice up. It doesn't matter if the drivers show up and cross the picket no trains can run. Either next Monday or the one following are the likely start dates, lines are walked on Monday, no walk = no train service
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
![]() |
#8 |
Member
Join Date: Dec 2005
Location: Northern line
Posts: 1,311
|
![]() So the permanent way staff were expecting to be chosen as sub contractors on the Midleton works? In what capacity?
|
![]() |
![]() |
![]() |
#9 |
Member
Join Date: Mar 2006
Posts: 30
|
![]() Token amount of track down at this stage and the grief is flowing already!
Are any staff arrangements in place for this extension and the corresponding new services? Stations / Signals / level crossings / train drivers? We are already seeing much disruption on off peak services to Cobh, is this the tip of the iceberg? |
![]() |
![]() |
![]() |
#10 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() Level crossings will be controlled from the Mallow center, already agreed and staffed
Signaling will be controlled from either Cork, Mallow or Connolly, requires fewer staff that current. Shortage of signaling staff has cancelled trains in the past 10 drivers in training in Cork The whole issue is down to staff in the permanent way are either Pre 2000 Mon-Fri limited night work Post 2000 far more flexible hours Contractors fill in generally at times of peak workload, eg night weekends, new works etc. Obviously is much cheaper not to pay overtime
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
![]() |
#11 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() Word in is the situation is interesting
Labour court ruled with the staff not management, it appears the dispute concerns lack of implementation on the Irish Rail management side of the agreement.
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
![]() |
#12 | |
Membership Officer
Join Date: Dec 2005
Location: Maynooth
Posts: 1,116
|
![]() Quote:
Or is it just the management in Cork who are more hopeless than the rest of the country? |
|
![]() |
![]() |
![]() |
#13 |
Chairman/Publicity
Join Date: Dec 2005
Location: The Home of Hurling
Posts: 2,708
|
![]() given what we know of what was supposed to happen last Friday and how it was everted - hint hint it's all in the members section folks - I think its a given that the cork managment are at best pathetic at worse pathological
|
![]() |
![]() |
![]() |
#14 | |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() You read it here virtually the day the strike notice was actually served
Quote:
Given they had 25 days up until now to fix it what difference is 48 hours going to make? Everything south of Portlaoise is effected, however services could stay running for a number of days until lines fall due for a visual inspection, by by Monday everything would be a risk Of course seat bookings are still being taken and no notice of any possibility of trouble is given by Irish Rail. EU regulations due to come into force in about 18 months will make it a legal requirement to inform at time of ticket purchase of any possible disruption
__________________
Unhappy with new timetable - let us know |
|
![]() |
![]() |
![]() |
#15 | |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() Its curious a notice appears now
Quote:
![]()
__________________
Unhappy with new timetable - let us know |
|
![]() |
![]() |
![]() |
#16 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() No solution today it appears
What will be effected? The Limerick Junction Permanent Way division is Portlaoise - Cork - Cobh Limerick -Limerick Junction - Waterford West Nenagh Branch Mallow - Tralee Since it includes Limerick station no Ennis services either It all depends on when the lines are walked. Note of course Irish Rail had 28 days notice, no published contingency plan. Many will recall when Aer Lingus was recently faced with a strike they had notices in papers and hired in planes from anywhere they could find them to keep things going. Irish Rail are saying nothing of course
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
![]() |
#17 | |
Membership Officer
Join Date: Dec 2005
Location: Maynooth
Posts: 1,116
|
![]() A bit of a last minute rush from Irish Rail management.
Note that the issue isn't resolved according to the report, just not going to impact on the bank holiday weekend. http://www.rte.ie/news/2008/0730/rail.html Quote:
|
|
![]() |
![]() |
![]() |