51 is the third contract option, 6 are from the first contract and will be numbered in the original sequence.

120+30+33+51

Neither have been paid for as payment is contingent on passing commissioning tests. Irish Rail have probably collected a considerable sum in penalties from Rotem due the issues with the 2 defective sets