09-09-2009, 15:50 | #41 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
Can confirm it was close to high tide at the time, that said the depth of water on the weir itself was nothing close to that, beyond the weir it varies starting at 2m
__________________
Unhappy with new timetable - let us know |
09-09-2009, 15:57 | #42 | ||
Local Liaison Officer
Join Date: Dec 2006
Posts: 5,442
|
Quote:
Quote:
__________________
|
||
09-09-2009, 19:56 | #43 | |
Local Liaison Officer
Join Date: Dec 2006
Posts: 5,442
|
http://www.rte.ie/news/2009/0909/rail.html
Quote:
__________________
|
|
10-09-2009, 08:58 | #44 | |
Member
Join Date: Feb 2009
Location: Lusk
Posts: 112
|
Independent, Thursday September 10 2009
http://www.independent.ie/national-n...s-1882404.html Quote:
|
|
10-09-2009, 09:01 | #45 | |
Member
Join Date: Feb 2009
Location: Lusk
Posts: 112
|
[quote=roamling;49312]Independent, Thursday September 10 2009
Quote:
Last edited by roamling : 10-09-2009 at 09:03. |
|
10-09-2009, 17:06 | #46 |
Member
Join Date: Dec 2005
Location: Northern line
Posts: 1,311
|
|
13-09-2009, 17:57 | #47 |
Regular Poster
Join Date: Nov 2006
Posts: 54
|
they still seem to be refusing to acknowledge lack of action to check the weir, you guys should be nailing them down on that.
|
16-09-2009, 07:07 | #48 | |
Member
Join Date: Feb 2009
Location: Lusk
Posts: 112
|
http://www.independent.ie/breaking-n...e-1887332.html
Quote:
|
|
16-09-2009, 12:24 | #49 | |
Member
Join Date: Feb 2009
Location: Lusk
Posts: 112
|
and a first glimpse whats going on in the hearing... at least somebody is asking the right questions...
Irish Times, September 16, 2009, 13:06 http://www.irishtimes.com/newspaper/...breaking38.htm Quote:
|
|
16-09-2009, 12:28 | #50 | |
Member
Join Date: Feb 2009
Location: Lusk
Posts: 112
|
Quote:
|
|
16-09-2009, 13:50 | #51 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
Like it or not, the full safety requirements where discharged by Irish Rail. The bridge was inspected in line with rail industry standards, all the inspections where in date (which is something that would not have been the case in the past). Put simply same viaduct in identical conditions in any well maintained rail network would have met the same fate.
Where the problem lies is in the unique construction of the Malahide viaduct, there are no foundations under the bridge, its built on a pile of rubble effectively and the whole show works on nothing more basic than gravity. The current presumed nature of the collapse is such that the rubble underneath the pier was pullled out by the water flow from the collapsed weir, until a point where gravity led the pier to fall over and the bridge collapses. Structurally an inspection even at 6pm on that Friday would have been unlikely to find anything amiss, I've seen a high res photo of the bridge taken at 6:10pm and there isn't a hint of anything wrong, the bridge looked fine. Only an underwater inspection would have revealed the problem, even then it would have been too late, the bridge would collapse in time. The failure was as a result of Irish Rail not understanding the relationship between the weir, the waterflow and the viaducts construction. Its classic accident territory not putting together all the pieces. Someone somewhere failed to identify the critical nature of the weir Most of all, finger pointing gets no one to work or home
__________________
Unhappy with new timetable - let us know Last edited by Mark Gleeson : 16-09-2009 at 13:59. |
16-09-2009, 14:19 | #52 |
Membership Officer
Join Date: Dec 2005
Location: Maynooth
Posts: 1,116
|
Hang on, someone paid handsomely to be RESPONSIBLE for safety and inspections needs to be help RESPONSIBLE.
Heads need to roll, the lack of accountability across every aspect of Irish Rail needs to be challenged and if a calamity of this scale fails to hold anyone in Irish Rail accountable, then what the hell do they have to wrong to be actually held RESPONSIBLE? |
16-09-2009, 14:38 | #53 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
Problem is the system won't let anyone hang since all the rules where complied with, the safety standards are as good as anywhere else in Europe, but still it went wrong. Had the inspections been out of date, you wouldn't have many senior staff left, if this had happened 10 years ago you would have been lucky to find a record of a bridge inspection and even luckier to find one which was in date.
Irish Rail goofed up since they failed to recognise the special characterisitcs of the Malahide viaduct, they seemed to understand the weir back in the 1960's but forgot about it up until now. Its classic accident stuff, not understanding the entire context
__________________
Unhappy with new timetable - let us know |
16-09-2009, 16:40 | #54 |
Member
Join Date: Feb 2009
Location: Lusk
Posts: 112
|
I think we have a right to highlight failures in scrutiny and pre-emptive measures to make 100% sure that the structure was safe. I feel deeply worried about the fact that people were put to risk because of a lack of full understanding of the interaction of water flows, viaduct constructions etc. The idea of an underwater inspection of a bridge structure that has been reported as possibly critical does not even require a fundamental understanding of the full context of these issues, it requires just a bit a common sense to make sure all aspects of the inspection have been ticked (and a bridge does not stop at the water level). It would have been a different case if the bridge had just collapsed without warning, but in this case there was a chance to prevent it and that is the point I want to highlight. There needs to be accountability within Irish Rail for these failures.
Last edited by roamling : 16-09-2009 at 16:44. |
17-09-2009, 07:25 | #55 | |
Member
Join Date: Feb 2009
Location: Lusk
Posts: 112
|
http://www.independent.ie/national-n...k-1888764.html
Independent September 17 2009 Quote:
|
|
17-09-2009, 08:48 | #56 |
Really Regular Poster
Join Date: Jan 2006
Posts: 767
|
There is too much grandstanding and playing blame-game going on here.
The politicians should be told that until the Railway Safety Authority has reported, they should exercise more restraint in what they say. It's pathetic how they play to the gallery. Some of the individuals have made extremely vindictive comments about people in other contexts and I would not trust them an inch. Why does there have to be such an atmosphere of witch-hunt about this? Loking for someone to hang, or fire or whatever? There may well be a reason to fire someone, but we will have to wait for the RSA report before we can pass such a judgement. There is even the possibility that this was a very freak one-off, which no-one could reasonaby foresee without the benefit of that marvellous gift: hindsight. Look at the aviation industry, which is surely the leader in good safety oversight. The emphasis in accident and indcident enquiries in aviation is to learn lessons that prevent future accidents. Whether anyone gets sacked or disciplined might of course happen, but the main emphasis is on finding the truth and learning lessons for the future. |
17-09-2009, 16:32 | #57 | |
Member
Join Date: May 2006
Location: Kazbegi
Posts: 281
|
Quote:
|
|
17-09-2009, 20:19 | #58 |
Member
Join Date: Apr 2007
Posts: 94
|
The Transport Committee transcripts are here: http://debates.oireachtas.ie/DDebate...Node=H3&Page=1 (Moderators please move if this fits better into another thread.)
|
18-09-2009, 07:23 | #59 | |
Member
Join Date: Feb 2009
Location: Lusk
Posts: 112
|
Quote:
|
|
18-09-2009, 09:15 | #60 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
As a previous poster has pointed out, there is far too much point scoring going on by some of our public representitives
The line of questioning at the joint committee was useless, no new information what so ever surfaced and indeed many of the questions where based on flawed information The RAIU guy played it by the book, investigation ongoing, we will publish a report, we will do so as quickly as possible Who do Irish Rail send out but Kenny, Lynch and Fearn, no sign of the chief engineer or safety officer. There is no question that something went wrong and in hindsight it should never have happened.
__________________
Unhappy with new timetable - let us know |
Thread Tools | Search this Thread |
Display Modes | |
|
|