Unread 05-01-2006, 08:16   #1
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default [Article] Serious flaws found in Luas system

You don't need to be an engineer to spot this one. The seal around the rail has been coming loose

Quote:
Originally Posted by Irish Times
Serious flaws found in sections of Dublin's Luas system
By Stephen Collins, Political Correspondent

Serious flaws in sections of Dublin's Luas light rail system have been identified in a comprehensive study commissioned by the contractors who built the lines, writes Stephen Collins, Political Correspondent

Repair work on nearly eight kilometres (five miles) of track has been recommended as a matter of urgency in the interests of long-term safety for passengers using the two lines.

The study, commissioned by AMB Joint Ventures who built the Luas lines, was carried out by the Institute for Railway Engineering at the University of Graz in Austria.

It identifies deficiencies in the bonding material under the rail in the city sections of both Luas lines. Approximately 6.4km of track on the Tallaght line and 1.3km on the Sandyford line are affected.

"The debonding is gradually more serious with sharper curvatures of the alignment and manifests itself by opening of fissures and cracks which permit penetration of water into the load-carrying system," according to the report.

It says that, so far, no reduction in operational safety had been observed, but concern was expressed about the future. "The development of bonding deficiencies gives rise to foresee a growing uncertainty towards the reliability and proper functioning of the system, particularly in tight curves."

The report says that even before the opening of the Luas lines, the tracks were beginning to show deficiencies. "After installation, a small number of blocks showed debonding, with frequent use by trams the number of affected blocks increased dramatically.

"After a short period of commercial tram operation (October 2004) already 32 per cent of blocks in straights and wide curves and 57 per cent of blocks in tight curves showed failures," says the report.

The report recommends that the track structure will have to be strengthened in the critical sections through a number of track-stiffening measures.

Fine Gael MEP Gay Mitchell, who has raised safety concerns about the system in the past, said yesterday that the report raised a number of issues.

"Firstly we need to know why this report was commissioned and what its cost was. We then need to know what the cost is going to be of putting right the deficiencies that have been identified so soon after the system was opened. Finally, we need to know what the safety implications are."
© The Irish Times 2006
http://www.ireland.com/newspaper/fro...LUASSTORY.html
Mark Gleeson is offline  
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 14:33.


Powered by vBulletin
Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.