Default 4/11/07 Transport 21. Sunday Business Post

Quote:
Almost all Transport 21 plans delayed

04 November 2007 By Pat Leahy, Political Correspondent

Almost every transport project due to be completed before 2010 under the government’s €34 billion Transport 21 plan is either already late or is expected to miss its original completion date.

Two years after the plan was announced by then transport minister Martin Cullen in 2005, documents released by the Department of Transport show that the targets for completing many projects have either not been met or are expected to be at least a year late.

At the launch of Transport 21 and for some time afterwards, the government’s catchphrase was ‘‘on time and on budget’’. However, while the true cost of the plan cannot yet be assessed, it is clear that the various elements of the plan will not be completed on time.

Revised schedules -many of which officials concede will be postponed again in the future - show that most projects scheduled to be completed this year are not expected to be finished until next year. Projects once expected to be completed in 2008 are now being given 2009 and 2010 completion dates.

The Department of Transport has also conceded that there is no operable date for a joining of the two Luas lines in Dublin city centre, following concerns expressed by Dublin Bus about the impact on bus traffic. The link-up was due to be finished next year.

Other projects which have slipped off the list of expected completions next year include Luas extensions to the Docklands and to Citywest in Dublin, and the Cork-Midleton commuter rail service.

The completion dates for many phases of the proposed Metro lines are being revised, although the department insists that they will all be completed by 2013 or 2014.

Most projects which have post-2010 completion dates are still expected to be on time, officials say. A statement issued by the Department of Transport explained that the original timetable was ‘‘designed to set challenging targets for the agencies’’.

‘‘Final completion dates for projects will only be determined when the planning process and contract negotiations have been concluded,” the department says.

Sadly, I am and have been of the opinion that this will only get worse.
Derek Wheeler is offline  
Unread 06-11-2007, 13:51   #2
clonsilladart
Regular Poster
 
Join Date: Jul 2006
Location: Clonsilla
Posts: 65
Default

Heard Derek yesterday on the Last Word.... points well made.
T21 (as far as rail is concerned) is beginning to look more and more like pie in the sky.

Just one thing, i noticed Matt used the "Platform 11" name to introduce you.....
clonsilladart is offline  
Unread 06-11-2007, 14:39   #3
ACustomer
Really Regular Poster
 
Join Date: Jan 2006
Posts: 767
Default

A statement issued by the Department of Transport explained that the original timetable was ‘‘designed to set challenging targets for the agencies’’.

Marvellous! A perfect example of the lying spin-doctor's black art!
ACustomer is offline  
Unread 08-11-2007, 12:46   #4
Colm Moore
Local Liaison Officer
 
Colm Moore's Avatar
 
Join Date: Dec 2006
Posts: 5,442
Default

Quote:
A statement issued by the Department of Transport explained that the original timetable was ‘‘designed to set challenging targets for the agencies’’.
=We put in blindly optimistic dates because there was an election coming up and matched them with some wild guesses.
Colm Moore is offline  
Unread 08-11-2007, 13:20   #5
Peter FitzPatrick
New to the board
 
Join Date: Mar 2006
Location: Dublin
Posts: 26
Default

Quote:
The Department of Transport has also conceded that there is no operable date for a joining of the two Luas lines in Dublin city centre, following concerns expressed by Dublin Bus about the impact on bus traffic. The link-up was due to be finished next year.
They can delay that one in to oblivion for all I care. Expensive pile of RPA nonsense.

Delays seem to be on the rail side, all interurban mortorways are either on time or ahead of schedule. Priorities.

Last edited by Peter FitzPatrick : 08-11-2007 at 13:26.
Peter FitzPatrick is offline  
Unread 11-11-2007, 20:46   #6
Colm Moore
Local Liaison Officer
 
Colm Moore's Avatar
 
Join Date: Dec 2006
Posts: 5,442
Default

Quote:
Originally Posted by Peter FitzPatrick View Post
Delays seem to be on the rail side, all interurban mortorways are either on time or ahead of schedule.
Well insofar as they were all meant to be finished at the end of 2006 ....
Colm Moore is offline  
Closed Thread


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 01:07.


Powered by vBulletin
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.