Quote:
Originally Posted by dowlingm View Post
Is the problem that the crossing trains are 6-car, ruling out a Castlerea crossing?
If that is the problem, either fit selective door opening (costs money and time), skip Castlerea (possibly unpopular) or only run three cars beyond Athlone (a different set might have to be rostered and again, possibly unpopular). Extra capacity is extra capacity - nobody will be losing anything, lots of people will gain. Alternatively make sure the train **from** Mayo is only 3-car and have it use the loop

Quote:
Ideally an N60 bypass or even a relief road might allow closure of the level crossing and extension of the loop platform to 176m which would add some flex to the timetable but clearly that's not on the cards for a LONG time.
Assuming it is signalled, the loop length doesn't seem to be the problem, just the platform and access - traditional style bridge.