Quote:
Originally Posted by ACustomer View Post
Should it really take 2 months closure? Could they not lay the cross-city line tracks up to a couple of meters from the existing tracks and then to the close-in work and the actual crossings in a series of night-time and weekend possessions?

I wonder how long the disruption lasts in other cities where existing lines are being added-to or crossed.
Bear in mind that the two junctions are adjacent to at least one hotel which does rule out night time works.

It's not just two lines crossing one another - there are sets of points to install at both locations on the existing tracks.