Jamie2k9: Thanks. It's a long closure for just 1.7km of track renewal (+ Lurgan platforms). I shudder to think what might be the impact of renewing all the rather bad track between Lurgan and Lisburn.
Irish Rail's use of weekend single-line working and night-time possessions on the Cork line seems to be much less disruptive.
|
Lisburn to Lurgan has already been refurbished, similar process to Cork line and carried out primarily at night during 2017 and 2018 using the Irish Rail based ballast cleaner with a few weekend closures to excavate and relay through various level crossings.