Given the circumstances it could not have been handled much better

1. On train communication was as nearly always a problem on many impacted services

2. No notice on Irish Rail's website

3. No communication of a clear plan

There is one option that was not considered, slight crazy but would have got folks home earlier, couple the 17:05 & 17:25 services and run to Athlone, Athenry, Gort, Limerick.

While it is a sensitive subject questions must be asked as to why it takes 5+ hours for the emergency services to deal with an incident like this. Consistently it takes 2-3 times as long to sort out an incident on the Heuston routes vs the DART, where 2 hours at most gets things running again