DART Development
The amended contract with Siemens for the completion
of the DART car refurbishment programme includes a
reduced number of vehicles being out of service for
refurbishment at any given time. This has enabled revised
DART car links to be implemented in the 2007 schedules,
significantly increasing the number of 8-car DART trains in
peak time operations, with the majority of peak services
now 8-car. This further increases peak time DART capacity
from the north and southside stations.
|
The capacity enhancements where implemented with 26 coaches out of service - before the revised agreement with Siemens came into force. Jan 13th was the date