dfl
02-03-2007, 21:04
Adamstown Station is due to open on the 10th of April.
Journey time approx 14 mins
The AM timetable announced is
Depart 7.04 7.28 7.59 8.29 9.04
PM from Heuston
Depart 16.05 17.18 18.05 18.50
The SDZ plan states the capacity per peak hour should be 600 passengers per hour AM and PM. This is indicative and not a planning condition like the 3000 capacity after the KRP.
Implies 240 spare places per train arriving in Adamstown in the am peak hours.
Implies 300 spare places per train departing from Heuston in the pm peak hours.
Given the current loading and capacity of the trains will this be met in the AM or PM or both?
If not what would Irish Rail need to do to deliver it?
Journey time approx 14 mins
The AM timetable announced is
Depart 7.04 7.28 7.59 8.29 9.04
PM from Heuston
Depart 16.05 17.18 18.05 18.50
The SDZ plan states the capacity per peak hour should be 600 passengers per hour AM and PM. This is indicative and not a planning condition like the 3000 capacity after the KRP.
Implies 240 spare places per train arriving in Adamstown in the am peak hours.
Implies 300 spare places per train departing from Heuston in the pm peak hours.
Given the current loading and capacity of the trains will this be met in the AM or PM or both?
If not what would Irish Rail need to do to deliver it?